Singapore version. Uses the 5x5 severity and likelihood matrix recommended in the WSH Council Code of Practice on Risk Management, with MOM's review and record-keeping rules. US version
WSH Risk Assessment Matrix (Singapore)
Rate severity and likelihood on the 5x5 matrix the WSH Council code recommends, get the RPN, and keep a register you can review every 3 years.
The interactive tool loads here when JavaScript runs.
About this toolWhat is the Risk Assessment Matrix?
Singapore is one of the few places where the 5x5 grid has official backing. The WSH Council's Code of Practice on WSH Risk Management (third revision, 2021) recommends a numeric 5x5 risk matrix, while leaving workplaces free to use another. Its risk prioritisation number is severity multiplied by likelihood, RPN = S x L, which is exactly the score this tool calculates: put severity in the Severity field and likelihood in the Likelihood field.
The code defines both scales. Severity runs from 1 Negligible (negligible injury) through 2 Minor (first aid only), 3 Moderate (medical treatment, such as burns, sprains or minor fractures) and 4 Major (serious injuries such as amputations or major fractures) to 5 Catastrophic (death or multiple major injuries). Likelihood runs from 1 Rare (not expected but possible) to 5 Almost Certain (continual or repeating). Rate both with existing controls in place, as the code instructs. The dropdown words in this tool (Very Low to Very High) are generic; read them as the code's names listed here.
The colour zones are your organisation's call. The code says the risk management team, with the employer's agreement, decides which cells count as Low, Medium and High, and then sets the actions: High must be brought down to at least Medium before work starts, and Medium must be reduced to as low as reasonably practicable within a defined period. The code's own Table 6 shades RPN 1 to 3 green (Low), 4 to 12 yellow (Medium) and 15 to 25 red (High). This tool's colours use different bands: 1 to 4 Low, 5 to 9 Medium, 10 to 16 High and 20 or 25 Critical, so they differ from the code at 4 (Low here, Medium in the code) and at 10 and 12 (High here, Medium in the code). Read the zone from the RPN against the code's bands, or record which zoning your organisation adopted on the risk assessment form.
- 5x5 grid with Low, Medium, High and Critical colour bands
- Score out of 25 and level badge for every risk
- Five risk categories and a mitigation field per risk
- JSON export and import, with ratings clamped to 1-5 on import
- Sample register for a product launch
Updated
How to use the Risk Assessment Matrix
- Set the assessment title, for example "Mobile app launch, Q1 2027".
- Click Add Risk, fill in the risk name and description, then pick Probability (1-5), Impact (1-5) and a Category: Operational, Financial, Strategic, Compliance or Technical.
- Write a mitigation strategy and click Add Risk in the form. The risk appears in its grid cell and in the Risk List with its score and level.
- Click Load Sample to see six scored risks for a mobile app launch.
- Use Export to save the register as JSON and Import to load it again; Clear All empties it.
Worked examples
Hot oil burns in an F&B kitchen
Input
Deep-frying station. Existing controls: trained cooks. Severity 3 x Likelihood 3. Additional controls: splash guard and heat-resistant gloves, re-rated Severity 3 x Likelihood 2
Output
RPN 9/25 Medium, then 6/25 Medium
Burns needing medical treatment are Moderate (3) in the code's severity guide. The extra controls reduce how often a splash injures someone, not how bad it is, so only likelihood moves. The re-rated RPN must not be higher than the first, and the code prefers that it ends in the Low zone where feasible, so look for an engineering control at the fryer itself before relying on gloves.
Hot work in a confined space at a shipyard
Input
Welding inside a tank. Severity 5 x Likelihood 2. With gas testing, permit-to-work and a fire watch: Severity 5 x Likelihood 1
Output
RPN 10/25 High, then 5/25 Medium
A fire or explosion is Catastrophic (5). On the code's Table 6 an RPN of 10 sits in the yellow Medium zone, so reduce it to as low as reasonably practicable within a defined period; this tool shades it High, which is stricter. After the controls, RPN 5 is still yellow (Medium) in the code. Permit-to-work is an administrative control, so record why nothing higher in the hierarchy (elimination, substitution, engineering) was practicable.
A paper guillotine in a small office
Input
Cuts from paper guillotine. Severity 2 x Likelihood 2
Output
RPN 4/25 Low
On the code's Table 6 an RPN of 4 is yellow (Medium), so check whether further controls, such as a blade guard, are reasonably practicable; this tool shades it Low. Whatever the zone, the code asks for review and monitoring so the rating does not drift as work changes.
Background and insight
Likelihood times impact is the oldest shortcut in risk management, and the 5x5 version is the one most project and operational risk registers use. ISO 31000 (the risk management guidelines, last revised in 2018) asks organisations to analyse likelihood and consequence but does not require a matrix or any particular bands; the bands here are a common convention, not a standard.
Because the scales are ordinal, a score of 12 is not "twice as risky" as 6. Only fourteen distinct scores are possible (1, 2, 3, 4, 5, 6, 8, 9, 10, 12, 15, 16, 20, 25), and a 5x1 risk (near certain, trivial) scores the same as a 1x5 risk (rare, catastrophic) even though most boards would treat them very differently. Louis Anthony Cox Jr. set out these problems in his 2008 paper "What's Wrong with Risk Matrices?" in Risk Analysis.
The practical fix is to define the scales before anyone scores. Write down what a 4 for impact means in money, days of delay or customers affected, and what a 3 for probability means as a rough percentage over a stated period. Without that, two people will score the same risk two levels apart and the grid becomes a record of who was in the room.
Common use cases
Project risk registers
Project managers score launch, migration or construction risks and review the red and orange cells at each steering meeting.
Operational and vendor risk
Ops and procurement teams rate supplier failure, outages and key-person dependencies on one grid.
Compliance and audit prep
Show auditors a dated register with scores and mitigations, exported as JSON for the evidence file.
Board and investor updates
Summarise the top risks visually instead of a long table.
Tips and limitations
- Choose controls in the code's order: elimination, then substitution, engineering controls, administrative controls and, last, personal protective equipment. High risks should not depend mainly on PPE.
- Show the matrix you used on every page of the risk assessment form. An RPN of 10 means different things on a 3x3 and a 5x5 grid.
- MOM's risk assessment form has S, L and RPN columns for both the existing and the additional controls; enter the same two ratings here to see the zone and keep the register.
- Build a multidisciplinary team: MOM lists management, engineers, supervisors, operators, maintenance, safety staff, contractors and suppliers.
Sources and further reading
- Code of Practice on Workplace Safety and Health Risk Management (third revision, 2021), Workplace Safety and Health Council. The recommended 5x5 matrix, severity and likelihood tables, RPN = S x L and actions by risk level.
- Risk management, Ministry of Manpower. Risk assessment steps, the hierarchy of control, the team and the risk assessment form.
- A Guide to the Workplace Safety and Health (Risk Management) Regulations, Ministry of Manpower. Review at least every 3 years and keep records for at least 3 years.
Frequently asked questions
Which risk matrix does Singapore's WSH code recommend?
The numeric 5x5 risk matrix, with severity and likelihood each rated 1 to 5 and the risk prioritisation number RPN = S x L. The code does not forbid other matrices, such as a 3x3, if they are described in enough detail for users.
How often must a WSH risk assessment be reviewed?
At least once every 3 years, according to MOM's guide to the Risk Management Regulations, and also after an accident caused by exposure to a hazard or when a significant change in work processes could affect safety and health.
How long must risk assessment records be kept?
For at least 3 years, by the employer, self-employed person or principal. The record should include the findings on the risk assessment forms, the control measures taken or planned, and any safe work procedures.
What must be done before work starts if the risk is High?
Under the code's recommended actions, a High risk must be reduced to at least Medium before work starts, without relying on interim measures, and management should review it first. If practicable, the hazard should be eliminated.
What steps does MOM expect in a risk assessment?
Three basic steps: hazard identification, risk evaluation and risk control, with control measures chosen by the hierarchy of control. Where a risk cannot be eliminated, safe work procedures must be set up and explained to workers.
Who must conduct a risk assessment in Singapore?
Every employer, self-employed person and principal, including contractors and sub-contractors, for routine and non-routine work at the workplace. They can do it themselves or engage a risk assessment consultant.
Is there an in-depth guide to the Risk Assessment Matrix?
Yes. “How to Use a 5x5 Risk Matrix (and Where Its Scores Mislead)” covers the background, how it works, common pitfalls and worked examples. Read the full guide.