Power Factor Correction Calculator (NSW Rules, 400 V 50 Hz)

Capacitor kVAr and µF to bring a 400 V, 50 Hz installation to the 0.90 lagging minimum in the NSW service rules (other states set their own).

The interactive tool loads here when JavaScript runs.

About this tool

What is the Power Factor Correction Calculator?

In NSW the Service and Installation Rules require customers to keep the maximum demand power factor of an installation between 0.90 lagging and unity, and power factor correction must never make it leading. This version starts on 400 V, 50 Hz and a delta-connected bank, and shows how much correction it takes to reach and pass that floor.

Enter the average kW at maximum demand, the power factor you measured and the target. The answer is the capacitor bank in kVAr, the µF of each capacitor and the drop in current and kVA. The multiplier beside the result is the same number tabulated in Table 6-1 of the NSW rules, so you can check one against the other.

Correction equipment needs the distributor's agreement before you commit to it, and it must not upset the ripple-control signals distributors inject to switch off-peak loads. That is often the deciding factor in how the bank is built.

  • kVAR from kW and two power factors, with the catalogue multiplier
  • Capacitance per capacitor for single-phase, delta and star at 50 or 60 Hz
  • Current, kVA and cable loss before and after
  • Scaled power triangle
  • Warnings for over-correction targets
Read the guide: Power Factor Correction: Sizing Capacitors in kVAR and µF

Updated

How to use the Power Factor Correction Calculator

  1. Enter the real power in kW. Use average demand from a bill or logger rather than a nameplate total.
  2. Enter the existing power factor and the target. 0.95 is a common target; going past 0.98 rarely pays and risks over-correction at light load.
  3. Enter the voltage (line to line for three-phase) and frequency.
  4. Choose single-phase, three-phase delta or three-phase star for the capacitor connection.
  5. Read the kVAR, the capacitance per capacitor, the current before and after, and the released kVA.

Worked examples

Workshop at 0.75: to the 0.90 floor and to 0.95

Input

120 kW, PF 0.75 to 0.90 and to 0.95, 400 V, 50 Hz, delta

Output

47.71 kVAr to reach 0.90 (230.9 A to 192.5 A); 66.39 kVAr to reach 0.95 (182.3 A)

The extra 18.7 kVAr for 0.95 frees another 7 kVA and 10 A. Whether that pays depends on how your network tariff charges for demand.

Checking against Table 6-1

Input

80 kW, PF 0.86 to 0.98, 400 V, 50 Hz, delta

Output

31.22 kVAr; multiplier 0.390; 207.1 µF per capacitor

Table 6-1 of the NSW rules gives 0.390 for 0.86 to 0.98, which matches. Multiply the kW by the table value to check any result quickly.

Old plant at 0.70, target 0.96

Input

40 kW, PF 0.70 to 0.96, 400 V, 50 Hz, delta

Output

29.14 kVAr; 82.5 A to 60.1 A, 27% less current

Table 6-1 gives 0.728 for this pair. Losses in the supply cables fall by about 47%, because they follow the square of the current.

Background and insight

Induction motors, transformers and fluorescent ballasts draw magnetising current that lags the voltage. That reactive current does no work, but it flows through every cable and transformer between the source and the load. Power factor, PF = kW ÷ kVA = cos φ, measures how much of the current is useful. Many utilities add a charge when the monthly PF falls below a threshold, commonly 0.9 or 0.95, or bill on kVA demand.

A capacitor draws leading reactive current that cancels part of the lagging current. With real power P unchanged, the reactive power before correction is P × tan φ1 and after is P × tan φ2, so the capacitor must supply Qc = P × (tan φ1 − tan φ2). Raising 100 kW from PF 0.70 to 0.95 needs 100 × (1.0202 − 0.3287) = 69.15 kVAR. Current falls in proportion to PF1 ÷ PF2, here by 26%, and cable losses (proportional to current squared) fall by about 46%.

Capacitance follows from Q = V² × 2πf × C for each capacitor. A single-phase capacitor across V needs C = Q ÷ (2πfV²). In a three-phase delta bank each of three capacitors sees the full line voltage and supplies Q ÷ 3, so C = Q ÷ (3 × 2πf × V²). In a star bank each sees V ÷ √3, which makes each capacitor three times larger: C = Q ÷ (2πf × V²). Delta banks are therefore usual at low voltage. Standard references include IEEE Std 18 for shunt power capacitors and IEC 60831 for low-voltage self-healing units.

Common use cases

  • Avoiding utility PF penalties

    Size a capacitor bank to keep the monthly power factor above the tariff threshold.

  • Freeing transformer capacity

    See how many kVA correction releases before buying a larger transformer.

  • Motor capacitor selection

    Find the µF for an individual motor capacitor at 50 or 60 Hz.

  • Teaching the power triangle

    Show how kW, kVA and kVAR relate before and after correction.

Tips and limitations

  • Apply to the distributor before buying or installing correction equipment; the NSW rules require an application for each connection except small units fitted to individual items of equipment.
  • Automatic banks must switch in steps small enough not to disturb the ripple-control frequency, and impedance improvement equipment may be needed. Discuss the design with the distributor before it is built.
  • A leading power factor is not allowed at any time, so a fixed bank sized for full load is a poor choice where the load drops at night or at weekends.
  • Shunt capacitors must comply with IEC 60831-1 for low-voltage self-healing units.

Sources and further reading

  1. Service and Installation Rules of NSW (April 2026), Section 6: Power factor correction, NSW Department of Climate Change, Energy, the Environment and Water. Clause 6.1.1 (0.90 lagging to unity, never leading), clause 6.2 (application, IEC 60831-1) and Table 6-1 (kVAr multipliers).
  2. IEC 60831-1:2014 Shunt power capacitors of the self-healing type for AC systems up to 1,000 V, International Electrotechnical Commission. IEC webstore entry for the capacitor standard the NSW rules cite.

Frequently asked questions

What power factor do I have to maintain in NSW?

Clause 6.1.1 of the Service and Installation Rules of NSW requires the customer to keep the maximum demand power factor of the installation between 0.90 lagging and unity. If it falls short, the distributor may require metering at an appropriate tariff. These are the NSW rules; other states and distributors set their own power factor requirements in their service and installation rules, so check yours.

Can I correct power factor all the way to 1?

You can aim close to it, but correction must never make the installation leading at any time. In practice that means an automatic bank that follows the load, and targets of 0.95 to 0.98 rather than unity.

Do I need approval to install a capacitor bank?

Yes, in NSW. Application must be made to the distributor for each connection of power factor correction equipment, except where it is fitted to individual items of equipment with low power requirements. Get agreement before you commit funds.

Why does the distributor care about ripple control?

Capacitor banks can absorb the audio-frequency signals that switch off-peak hot water and other controlled loads. Rules require the bank not to affect that system, which may mean impedance improvement equipment or detuning.

Will power factor correction cut my power bill?

The NSW rules note that the cost can usually be recovered through lower electricity costs. The savings come from kVA-based demand charges and avoided tariff penalties, not from the energy the load uses, so check how your network tariff bills demand.

Should I use the delta or star option?

Most low-voltage banks are delta-connected at 400 V. Star needs three times the capacitance for the same kVAr, at 230 V across each capacitor.