India version. Metric by default, with IS 1786 TMT bar sizes, the D²/162 kg per metre rule, 12 m bars, IS 456 covers and 57-diameter laps, and the cost of steel in rupees. US version

Steel Quantity Calculator for Slab and Footing

Number of TMT bars, cutting length, laps and steel weight in kg for a slab, footing or raft in 8 to 32 mm Fe 500 bars, using D²/162 and 12 m bar lengths.

The interactive tool loads here when JavaScript runs.

About this tool

What is the Rebar Calculator?

On Indian sites steel is ordered by weight, so the question is how many kilograms of TMT bars a slab or footing needs. The quick rule is that a bar of diameter D mm weighs D²/162 kg per metre: 0.395 kg/m for 8 mm, 0.617 kg/m for 10 mm, 0.888 kg/m for 12 mm and 1.579 kg/m for 16 mm. This version uses those IS 1786 nominal masses and 12 m bar lengths.

Enter the slab or footing size, the clear cover and the bar spacing each way. The tool counts the bars, adds laps where a bar is longer than 12 m, and gives the total length, the weight and the number of 12 m bars to buy, with the offcuts. Covers come from IS 456: 20 mm for slabs in mild exposure, 30 mm in moderate exposure and 50 mm for footings. TMT bars sold in India must conform to IS 1786 and carry the BIS (ISI) mark.

  • US bar sizes #3 to #11 with ASTM A615 weights and metric 8 to 32 mm bars
  • Single or double mats, edge cover, hooks and lap splices
  • Stock-length cutting estimate with offcut and lap count
  • Steel area per foot or per metre of width for design checks
  • Copy, share link and cost per stock bar; runs in your browser
Read the guide: Rebar Takeoff for Slabs: Bar Counts, Laps, Cutting and Weight

Updated

How to use the Rebar Calculator

  1. Pick imperial or metric. Plan dimensions are in feet or metres; cover, spacing and laps are in inches or millimetres.
  2. Enter the slab or footing length and width and the edge cover. Add a hook or bend length per end if the bars turn up at the edges.
  3. Choose the bar size and the centre-to-centre spacing of the bars running along the length and along the width.
  4. Select a single mat or top and bottom mats, the stock length your supplier sells, and the lap length in bar diameters or as a length.
  5. Read the bar counts, total length, weight and stock bars to buy, then copy the takeoff or share a link with the inputs.

Worked examples

Room slab, 4.5 x 3.6 m, 10 mm bars at 150 mm both ways

Input

4.5 x 3.6 m, cover 20 mm, 10 mm @ 150 mm each way, one mat, 12 m bars

Output

54 bars, 213.84 m, 131.9 kg; 22 bars of 12 m

A real two-way slab has main bars, distribution bars, cranks and extra top steel at the supports, which come from the structural drawing. Use this as a first check on the steel the contractor quotes.

Isolated footing, 2 x 2 m, 12 mm at 150 mm

Input

2 x 2 m, cover 50 mm, 12 mm @ 150 mm each way, one mat, 12 m bars

Output

26 bars of 1.9 m, 43.9 kg; 6 bars of 12 m

The 50 mm cover is the IS 456 minimum for footings (26.4.2.2). Each 12 m bar gives six 1.9 m pieces; the tool does not share offcuts between the two directions, so each set of 13 pieces takes 3 bars, 6 in all.

Raft, 14 x 9 m, 16 mm at 150 mm, top and bottom

Input

14 x 9 m, cover 50 mm, 16 mm @ 150 mm each way, two mats, 12 m bars, lap 57 diameters (912 mm)

Output

306 bars, 3,432.84 m, 5,420.5 kg (about 5.4 tonnes); 120 laps; 336 bars of 12 m

The 13.9 m bars need one lap each. A lap of about 57 diameters is the development length of Fe 500 bars in M20 concrete under IS 456 (26.2.1); use the length on your drawing.

Background and insight

The bar count uses the fence-post rule: a clear width of W - 2c at spacing s holds floor((W - 2c) / s) + 1 bars, with a bar at each edge. Counting only (W - 2c) / s is the classic takeoff error that leaves you one bar short on every run. Bars along the length are spaced across the width, so the two directions swap dimensions.

When a bar run is longer than the stock length, it is made from n pieces that overlap by the lap length, so n pieces cover n x S - (n - 1) x lap and n = ceil((run - lap) / (S - lap)). The lap itself is a design value. ACI 318 sets tension lap splices at 1.0 or 1.3 times the development length, which depends on concrete strength, bar size, cover and position; 40 bar diameters is a common starting value on site drawings, not a code check. Cover also comes from the code: ACI 318 asks for 3 in where concrete is cast against and permanently exposed to earth, which is why footings use 3 in (75 mm).

Common use cases

  • Ordering steel for a slab on grade

    Turn a spacing note such as "#4 @ 12 in EW" into a piece count and a weight that a supplier can quote.

  • Checking a fabricator quote

    Compare the supplier's weight and bar list against an independent takeoff before the delivery arrives.

  • Footings and mat foundations

    Add hooks at each end and a second mat to estimate a spread footing or raft.

  • Comparing bar size against spacing

    Swap #4 at 12 in for #5 at 16 in and compare steel area per foot, weight and the number of bars to tie.

Tips and limitations

  • Check the ISI mark and the grade (Fe 500, Fe 500D) rolled on to the bar; the Steel Quality Control Order requires IS 1786 bars to be BIS certified.
  • Ask the dealer whether the price is per kg or per tonne and whether cutting, bending and binding wire are included.
  • Keep 2 to 3% extra for wastage at bends and the last piece of each bar.
  • The price field is per 12 m bar, while dealers quote per kg: multiply the rate by the bar weight. A 12 m bar of 10 mm weighs 7.4 kg, so ₹65 per kg is about ₹481 a bar.
  • For the weight per metre of each bar size, or the weight of a given length, use the [Steel Weight Calculator](/steel-weight-calculator).

Sources and further reading

  1. Handout on Indian Standards on Building Materials, Bureau of Indian Standards. IS 1786 for high strength deformed bars and the Fe 415, Fe 500 and Fe 550 grades. The chemistry and elongation of the D grades are in IS 1786:2008, Tables 1 and 3.
  2. Quality Control Orders for steel products (Lok Sabha unstarred question 3149), Ministry of Steel, Government of India. IS 1786 bars are among the steel products that must carry the BIS mark.
  3. IS 456:2000 Plain and Reinforced Concrete: Code of Practice, Bureau of Indian Standards (copy at Public.Resource.Org). Nominal cover (26.4, Table 16), development length (26.2.1) and laps (26.2.5).

Frequently asked questions

How do I calculate steel weight per metre?

Weight in kg/m = D² / 162, with D in mm. It comes from pi/4 x D² x 7,850 kg/m³. For 8, 10, 12, 16, 20, 25 and 32 mm bars that gives 0.395, 0.617, 0.888, 1.579, 2.466, 3.854 and 6.313 kg/m.

How much steel is required for a slab per square foot?

It depends on the design, so calculate it from the bar size and spacing. The 4.5 x 3.6 m slab above, with 10 mm bars at 150 mm both ways, uses 131.9 kg over 16.2 m², about 0.75 kg per square foot for the bottom mesh alone, before top steel at the supports.

What is the clear cover for slab, beam, column and footing as per IS 456?

By exposure (Table 16): 20 mm mild, 30 mm moderate, 45 mm severe, 50 mm very severe and 75 mm extreme. Columns need at least 40 mm for main bars (26.4.2.1) and footings at least 50 mm (26.4.2.2).

What is the lap length for TMT bars?

For bars in flexural tension IS 456 26.2.5.1 asks for the development length Ld or 30 diameters, whichever is greater; in direct tension, 2Ld or 30 diameters. For Fe 500 bars in M20 concrete Ld works out to about 57 diameters, so a 12 mm bar needs about 680 mm.

What is the difference between Fe 500 and Fe 500D?

Both have a 500 N/mm² yield strength under IS 1786:2008. The D grade has tighter limits on carbon, sulphur and phosphorus (Table 1) and higher elongation (Table 3), which gives more ductility and is often specified in seismic zones.

How many 12 mm bars are in one tonne?

A 12 m length of 12 mm bar weighs 12 x 0.888 = 10.66 kg, so a tonne is about 94 bars. For 10 mm it is about 135 bars and for 16 mm about 53.

Is there an in-depth guide to the Rebar Calculator?

Yes. “Rebar Takeoff for Slabs: Bar Counts, Laps, Cutting and Weight” covers the background, how it works, common pitfalls and worked examples. Read the full guide.