United Kingdom version. Metric by default with BS 4449 bar sizes 6 to 40 mm (H6 to H40), masses in kg/m, stock lengths of 6 m and 12 m and a lap set in bar diameters. US version
Rebar Calculator (UK, BS 4449 Bar Sizes)
Count H10, H12 or H16 bars for a slab, raft or footing mat, with BS 4449 masses in kg per metre, laps in bar diameters and 6 m or 12 m stock bars.
The interactive tool loads here when JavaScript runs.
About this toolWhat is the Rebar Calculator?
UK drawings call up reinforcement by grade and diameter: H12 at 200 centres means a 12 mm high-yield bar (grade B500 to BS 4449) every 200 mm, and the bar schedule follows BS 8666. Steel is bought by weight, so the useful answer is the number of bars, the cut lengths and the kilograms. This version uses the BS 4449 nominal masses, from 0.222 kg/m for 6 mm bar to 9.865 kg/m for 40 mm.
Enter the slab or raft size, the cover, the bar and the spacing each way, and choose one mat or top and bottom mats. The tool counts the bars, adds laps where a run is longer than the stock bar, nests the offcuts and gives the weight and the number of 6 m or 12 m bars to order. Many domestic slabs use fabric mesh such as A142 or A393 sheets instead, which this tool does not count.
- US bar sizes #3 to #11 with ASTM A615 weights and metric 8 to 32 mm bars
- Single or double mats, edge cover, hooks and lap splices
- Stock-length cutting estimate with offcut and lap count
- Steel area per foot or per metre of width for design checks
- Copy, share link and cost per stock bar; runs in your browser
Updated
How to use the Rebar Calculator
- Pick imperial or metric. Plan dimensions are in feet or metres; cover, spacing and laps are in inches or millimetres.
- Enter the slab or footing length and width and the edge cover. Add a hook or bend length per end if the bars turn up at the edges.
- Choose the bar size and the centre-to-centre spacing of the bars running along the length and along the width.
- Select a single mat or top and bottom mats, the stock length your supplier sells, and the lap length in bar diameters or as a length.
- Read the bar counts, total length, weight and stock bars to buy, then copy the takeoff or share a link with the inputs.
Worked examples
Garage slab, 6 x 3 m, H12 at 200 one way and the other
Input
6 x 3 m, cover 50 mm, H12 @ 200 both ways, single mat, 6 m stock bars, lap 40 diameters
Output
45 bars, 175.5 m, 155.8 kg; 30 stock bars of 6 m
Every bar fits inside a 6 m stock length, so there are no laps. Fifteen 5.9 m bars each use a full stock bar, while the thirty 2.9 m bars pair up two to a bar.
Raft, 15 x 8 m, H12 at 200, top and bottom
Input
15 x 8 m, cover 40 mm, H12 @ 200 both ways, two mats, 12 m stock bars, lap 40 diameters (480 mm)
Output
230 bars, 2,420 m, 2,149 kg; 80 laps; 258 stock bars of 12 m
The 14.92 m bars are longer than a 12 m stock bar, so each needs one lap. The lap length used here is a starting value only; Eurocode 2 lap lengths depend on concrete class, bond conditions and the percentage lapped, so take the figure from the engineer's drawings.
Background and insight
The bar count uses the fence-post rule: a clear width of W - 2c at spacing s holds floor((W - 2c) / s) + 1 bars, with a bar at each edge. Counting only (W - 2c) / s is the classic takeoff error that leaves you one bar short on every run. Bars along the length are spaced across the width, so the two directions swap dimensions.
When a bar run is longer than the stock length, it is made from n pieces that overlap by the lap length, so n pieces cover n x S - (n - 1) x lap and n = ceil((run - lap) / (S - lap)). The lap itself is a design value. ACI 318 sets tension lap splices at 1.0 or 1.3 times the development length, which depends on concrete strength, bar size, cover and position; 40 bar diameters is a common starting value on site drawings, not a code check. Cover also comes from the code: ACI 318 asks for 3 in where concrete is cast against and permanently exposed to earth, which is why footings use 3 in (75 mm).
Common use cases
Ordering steel for a slab on grade
Turn a spacing note such as "#4 @ 12 in EW" into a piece count and a weight that a supplier can quote.
Checking a fabricator quote
Compare the supplier's weight and bar list against an independent takeoff before the delivery arrives.
Footings and mat foundations
Add hooks at each end and a second mat to estimate a spread footing or raft.
Comparing bar size against spacing
Swap #4 at 12 in for #5 at 16 in and compare steel area per foot, weight and the number of bars to tie.
Tips and limitations
- Cap or bend over projecting starter bars: HSE guidance on protecting the public lists falls onto projecting reinforcement among the hazards on building sites.
- Order to the bar schedule (BS 8666 shape codes) where there is one; the tool's count is a check, not a replacement.
- Allow for chairs and spacers to hold the cover, and for tying wire, which the weight here does not include.
Sources and further reading
- Protecting the public: your next move (HSG151), Health and Safety Executive. Falls onto projecting reinforcement bars on construction sites.
- Standards for reinforcement, The Concrete Centre. BS 4449 grades B500A, B500B and B500C and BS 8666 scheduling.
Frequently asked questions
What does H12 at 200 mean?
A 12 mm high-yield bar (grade B500 to BS 4449) at 200 mm centres. On older drawings "T12" means the same high-tensile bar. B500 has a characteristic yield strength of 500 MPa.
How much does 12 mm rebar weigh per metre?
0.888 kg per metre. The BS 4449 nominal masses follow pi/4 x d² x 7,850 kg/m³: 10 mm is 0.617 kg/m, 16 mm 1.579 kg/m, 20 mm 2.466 kg/m and 25 mm 3.854 kg/m.
What lap length should I use for rebar in the UK?
Take it from the engineer's design. Lap lengths under Eurocode 2 (BS EN 1992-1-1 and its UK National Annex) depend on concrete strength, bond conditions, cover and how many bars are lapped at one section. The tool's 40 diameters is only a starting value; enter the drawing's figure in diameters or in millimetres.
What stock lengths does UK rebar come in?
Straight bar is usually sold in 6 m and 12 m lengths, and suppliers will also cut and bend to a BS 8666 schedule. The tool assumes you buy whole stock bars and shows the offcut left over.
Should I use mesh or loose bars for a slab?
Domestic ground slabs and garage bases are often reinforced with fabric mesh sheets (A142, A193, A252, A393) because they are quicker to lay. Loose bars are used where the design calls for a specific bar size or spacing, at openings and edges, or in rafts and footings.
Is there an in-depth guide to the Rebar Calculator?
Yes. “Rebar Takeoff for Slabs: Bar Counts, Laps, Cutting and Weight” covers the background, how it works, common pitfalls and worked examples. Read the full guide.
Related Tools You May Like
Free, in-browser tools that pair well with this one.